Objective: Understand what currently exists and identify what works, what doesn't, and what's missing.
Tasks: Review all existing pages and features.
Deliverable: Feature Inventory Summary with recommendations per module.
Estimated duration: 7 days
Objective: Generate new ideas, improvments, and potential new features.
Tasks:
- Use yellow stickies to propose:
- New features or functionalities
- UX/UI improvments
- Group all ideas by category (Goals, Insights, Banking, Settings, etc).
- Discuss as a team and refine each idea.
Deliverable: List of new and improved features grouped by module
Estimated duration: 14 days (Deadline 28.10.2025)
Objective: Decide what features go into the MVP redesign and what goes into future phases.
Tasks:
- Use a prioritization system (Impact vs. Effort).
- Vote as a team for each idea or feature.
- Define three groups:
- MVP features - must have
- Future roadmap - nice to have
- Not relevant - remove or pause
Deliverable: Feature Priority Map (visual board of prioritization)
Estimated duration: 1-2 days (Deadline: 30.10.2025)
Objective: Redefine the app flow and structure based on approved features.
Tasks:
- Create a new sitemap for the app.
- Define user flows for key features (e.g., adding a transaction, setting a goal).
- Review usability and navigation consistency.
- Start early wireframe sketches for complex screens.
Deliverable: Updated app structure + initial UX wireframes.
Estimated duration: 7-14 days (Deadline: 10.11.2025)
Objective: Translate wireframes into visual design aligned with Finance.io branding.
Tasks:
- Redesign visual style and components.
- Prepare interactive protoype for user testing.
- Refine based on feedback and team reviews.
Deliverable: High-fidelity protoype ready for testing.
Estimated duration: 14 days (Deadline: 24.11.2025)
Objective: Finalize all screens and documentation for developers.
Tasks:
- Conduct internal review sessions.
- Prepare design documentation, component guidelines, and assets.
- Deliver final prototype to dev team.
Deliverable: Design System + Developer Handoff package.
Estimated duration: 7 days (Deadline 30.11.2025)
The Developer Handover: 30.11.2025
Tasks:
- Create Issues / Tickets for each Task.
- Prioritize the tasks
- Assign the tasks
Deliverable: Plan for the nexts weeks, everyone knows his task
Estimated duration: 1 day (Deadline 01.12.2025)
Tasks:
- Building the Dashboard UI and Backend
- Building the Analyse Pages UI and Backend
- Building the UI and Backend for Transaction Pages
Deliverable:
Estimated duration: 14 days (Deadline 15.12.2025)
-- Will add more later --